Spruce Court
Enabling works will begin at Spruce Court.
Works on flats at Spruce Court will commence
Full works on all sales properties will commence.
Full works on the remaining properties will commence.
Works to demolish 6, 21 and 22 commence
Demolition of 6, 21 and 22 finished, render and cladding applied to homes except those next to demolition units
For driveways, fencing and roads
Solar power and batteries installed in our homes
Commence internal works for court side drives, roads and gardens.
Complete and let flat conversions
Internal works for court side drives, roads and gardens complete.
New road to Spruce court completed.
Install barriers to prevent vehicles accessing the football field
Spruce Court completed for handover and remaining homes to be let.